On September 3rd - December 7th 2007, St Mary's Church underwent Re-ordering.
This is how the church looked before work began.
.
.
.
.
New plumbing and wiring went in, blown glass insulation sub floor covered it, then limecrete instead of concrete was poured on top for the floor base.
.
The font is relocated. The underfloor heating is laid and the tea-bar starts to take form.
The solid oak wood floor is laid, and the oak panelling is mounted around the tea-bar.
Finally, the matching arch is completed, fittings are made to the toilet,and the chairs arrive just in time for our first service on 16th December 2007. The first new layout of the chairs was used for the Christingle Service on January 6th 2008.